TruStile Doors

Denver Headquarters

Denver, CO

Project Type

New construction of a 200,000 GSF of composites and wood manufacturing facility with 50,000 GSF of office space and showroom. Maxson Engineering and the design team were able to utilize production waste to generate on-site heating water via bio-mass boilers to cut down on energy consumption and product waste.

Project Type

Renovation

Square Footage

273,000

Construction Budget

$70 million

Project Delivery Mode

DesignBuild

Project Highlights:

  • Bio-mass Boiler Heating Water Generator

  • Central Chilled Water and Heating Water Plants

  • Process Chilled Water

  • Central Utility Plant (CUP) Building

  • High Efficiency HVAC

  • Process Compressed Air Distribution

  • Dust Collection

  • Natural Gas Generator

  • Paint Line Drying System